Street Closings

Below is a list of streets that are currently closed for various construction projects, and the dates they are closed.

When closures are necessary, we make every effort to coordinate work to minimize impact to motorists, pedestrians and area businesses.

Road Closed (image)

Weather and unforeseen circumstances occassionally prevent work from being completed and make it unsafe to reopen lanes or streets as planned. If this occurs, our traffic engineers work with other City staff and contractors to resolve the situation as quickly as possible and reduce further impacts to the traveling public.

NASCAR Hall of Fame Complex - Road Improvements

The I-277/Caldwell Interchange Project (NASCAR Hall of Fame Road Improvements) will reconstruct several ramps on I-277 and modify Stonewall, Caldwell and Brevard Streets along with Martin Luther King Boulevard in uptown Charlotte.  When completed, the area in and around the interchange will be pedestrian and bicycle friendly and accommodate development of the future NASCAR Hall of Fame site.  Construction of the interchange project is scheduled to be complete when the NASCAR Hall of Fame opens in 2010.  For the latest information about the project, visit the website nascarhof.charmeck.org.

Road and/or Lane Closures
Click here for more details about the road closures below.

  • East Fourth Street -- January 3 - 4, 2009
  • North College Street -- December 19 - 22, 2008
  • Intersection of Ferncliff Road, Audubon Road, and Coventry Road -- December 10, 2008 - February 10, 2009
  • Carson Boulevard -- November 21-22, 2008
  • Westbound Stonewall Street -- November 21 - 25, 2008
  • UPDATED - Remount Road/Barringer Drive -- September 17, 2008 -  to January 9, 2009
  • I-277/Caldwell Street Interchange Project -- October 21 - December 1, 2008
  • Fifth Street -- September 22 - November 22, 2008 Coventry Road -- September 15 - January 15, 2008 UPDATED Michael Baker Place -- Change from -November 12, 2007 through August 18, 2008  (Nine Months)  to November 12, 2007 through February 27, 2009 (15 months)
  • West First Street -- June 27, 2008 throughout construction
color bar graphic
View Text-Only
Print This Page
Events Calendar
311 Web Requests
Maps/GIS Locator
Notify Me
Site Help
Feedback

- Parade Permit Application

Latest Street Use Notice (SUN)
 -SUN Calendar

- Parking Rules
- Bank of America Stadium Parking

logo
Official City of Charlotte & Mecklenburg County Government Web Site